Plan and milestones log
Planned milestones for Kestrel Power, dated. These are plans and targets, not completed events. Nothing here has happened yet. We will update this page when a milestone is met or moves.
4 January 2027: planned launch
Trading starts from the Wacol depot, Brisbane QLD 4076, with a Queensland electrical contractor licence in place. The Powerlink pre-qualification application is lodged in Month 1.
February 2027: planned
Energy Queensland accredited service provider application lodged (Month 2).
End of March 2027: planned headcount 14
End of Q1 target of 14 staff. The test lab at the depot is planned to be operating, with the first owned test equipment in use.
May 2027: planned
ISO 45001 and ISO 9001 stage 1 audit (Month 5).
June 2027: planned
Targeted approvals for Powerlink pre-qualification and Energy Queensland accreditation (Month 6). Essential Energy and Transgrid applications lodged. End of Q2 target of 38 staff.
Q3 2027: planned
Satellite laydown yard at Yatala, Gold Coast (2,000 m2) planned to open. ISO 45001 and ISO 9001 certification targeted for September, with Essential Eight Maturity Level 2 by the same date. End of Q3 target of 64 staff.
December 2027: planned
Essential Energy and Transgrid approvals targeted (Month 12). End of Q4 target of 90 staff and a Q4 revenue run-rate plan of $48 million a year.
2028 (Year 2): planned
ISO 14001 certification targeted. 275 kV work delivered with a partner, with Kestrel self-performing 11 kV to 132 kV.