Five phases. Five exit gates.
Five phases take a package from design interface to handover, each closed by an exit gate. A named commissioning lead is on every project from award.

10
Late design changes and late plant orders push out the energisation date. Long-lead plant sets the critical path.
Design interface reviews at 30, 60 and 100%, with the commissioning lead signing. Long-lead plant is ordered within 10 business days of design freeze and witnessed at FAT, so the date is protected before anyone is on site.
30
On site, one missed shutdown or network approval slips the whole programme. Approvals and outages are routinely the constraint.
One Site Supervisor per site, a Friday three-week look-ahead and a weekly float report. A readiness review 30 days before energisation checks protection settings, plant, approvals and test records.


30
An energised asset is only useful if its records are complete. Missing settings files and test records cost months later.
As-builts, test records and relay settings files are handed over complete, and the team supports the asset for 30 days after energisation. Maintenance and testing work can follow from the same crew.