A 33 kV zone substation for a Richlands data centre, planned to an energisation date.
Delivery brief
.
21 Nov 2026

A 33 kV zone substation for a Richlands data centre, planned to an energisation date.

Placeholder portrait image, not a real person
Kestrel Power planning team
Illustrative delivery brief — not a completed project

Client

None (illustrative)

Sector

Data centre

Scope

33 kV zone substation

Region

Brisbane, Qld

Load had a date before the network had capacity.

Assumption: a data centre operator at Richlands needs a 33 kV zone substation energised to a fixed date for its first hall. Network capacity is congested, so the date depends on network approvals, long-lead transformers and switchgear, and commissioning that starts before the civils finish.

The risk is not the construction. It is a date that slips quietly because an approval, a delivery or a settings file had no owner. This brief is a planning scenario with no client and no completed work behind it.

Programme · five phases
Illustrative, not measured

Five phases, each with an exit gate.

Design interface with 30, 60 and 100% reviews, signed by the commissioning lead. Long-lead plant ordered within 10 business days of design freeze, with factory acceptance tests witnessed. One Site Supervisor on site, a Friday three-week look-ahead and a weekly float report.

Commissioning is prepared against a readiness review 30 days before energisation, then handover of as-builts, test records and settings files with 30 days of post-energisation support. The network service provider owns energisation approval.

What the plan targets.

Assumptions, not results: transformers up to 100 MVA, civils subcontracted, network settings issued by the network service provider and implemented and tested by Kestrel. The target is energisation on the contracted date, priced with a schedule certainty premium of 2–4% and delay damages capped at 10% of contract value.

30 days
Readiness review before energisation
10 days
Business days to order long-lead plant
0
Lost-time injuries (target)

Where it would repeat.

If a repeat package followed, the same phases and gates would apply across further halls in the same precinct. That is a hypothesis, not a pipeline: Kestrel has no client and no contract for this scenario.